Advanced Product Quality Planning (APQP)

SkillDev tools

Advanced Product Quality Planning (APQP), plan and track a new product launch through all 5 phases, identify deliverables per phase, run gate reviews, and ensure quality outputs are complete before Start of Production (SOP). Use when launching a new part, managing an APQP project, or auditing APQP completeness. Covers AIAG APQP 2nd edition and IATF 16949 §8.3.

Use Advanced Product Quality Planning (APQP) in Claude, ChatGPT or Ahel Desktop

Free. Sign in, add Advanced Product Quality Planning (APQP) and connect your AI. About a minute.

Also: Claude Code · Cursor · Codex

Then ask your AI: use the Advanced Product Quality Planning (APQP) skill

Details

Instructions available. Your AI can read the instructions. Execution depends on the setup they require.

Add Ahel to your AI once: Claude, ChatGPT, Cursor, Claude Code or Codex. Then ask it to use this.

Advanced Product Quality Planning (APQP)Start free

What this skill tells your AI

The instructions your AI receives, as published by hashgraph-online/awesome-codex-plugins in plugins/RBraga01/Quality-Engineering-Skills/skills/planning/apqp/SKILL.md and read by Ahel’s review.

When to use

Use this skill when:

  • A new product or part is being launched and a structured quality plan is needed
  • Managing an APQP project and tracking deliverables across phases
  • Conducting an APQP gate review to assess launch readiness
  • A customer requests an APQP status report or phase completion confirmation
  • Auditing whether a supplier's APQP process is adequate

Prerequisites

  • Customer requirements, specifications, and drawings (or RFQ package)
  • Programme timing (SOP date, PPAP submission date, prototype gates)
  • Nominated APQP team (cross-functional: engineering, quality, purchasing, manufacturing, logistics)
  • Customer APQP template if OEM-specific format required

Workflow

Overview — The 5 APQP Phases

Phase 1          Phase 2          Phase 3          Phase 4          Phase 5
Plan & Define → Product Design → Process Design → Product & Process → Feedback &
                & Development   & Development      Validation         Corrective Action
     ↓               ↓               ↓                ↓                  ↓
  Program         Prototype       Pre-launch         PPAP              SOP +
  approval         build           build           submission          Production

All phases run with concurrent engineering — phases overlap and teams work in parallel.


Phase 1 — Plan and Define Program

Objective: Understand customer requirements and define what the product must do.

Key deliverables:

DeliverableDescription
Voice of the Customer (VOC)Customer wants, needs, expectations — translated to measurable requirements
Design GoalsProduct performance targets derived from VOC
Reliability and Quality GoalsTarget failure rate, warranty targets, Cpk targets
Preliminary Bill of MaterialsDraft BOM from design intent
Preliminary Process FlowHigh-level process sequence
Preliminary Special CharacteristicsInitial list of critical/significant characteristics
Product Assurance PlanQuality plan for the programme
Management SupportSigned-off programme charter with resources and timing

Gate 1 pass criteria:

  • Customer requirements documented and agreed
  • Feasibility confirmed (technical and commercial)
  • Team chartered and timing plan approved
  • Special characteristics list preliminary but complete

Phase 2 — Product Design and Development

Objective: Translate customer requirements into a product design with verified characteristics.

Key deliverables:

DeliverableDescription
DFMEADesign FMEA — all failure modes analysed, H-AP items addressed
Design Verification Plan (DVP)Test plan linked to DFMEA failure modes
Drawing and Specification ReleaseFully released engineering drawings and 3D data
Material SpecificationsRaw material specs, supplier approval plan
Drawing and Specification ChangesChange management process in place
New Equipment and ToolingList of new equipment/tooling required
Special Product and Process CharacteristicsUpdated with design detail
Gauge PlanMSA requirement list — which characteristics need MSA studies
Prototype Control PlanControl plan for prototype builds
Prototype BuildPrototype parts manufactured and tested
Engineering DrawingsReleased and approved

Gate 2 pass criteria:

  • DFMEA complete with all H-AP actions closed
  • DVP complete and test execution started
  • Prototype build results acceptable
  • All special characteristics identified and confirmed
  • No outstanding major design concerns

Phase 3 — Process Design and Development

Objective: Design and verify the manufacturing process.

Key deliverables:

DeliverableDescription
Packaging StandardsPackaging design, labelling, MMOG/LE if required
Product/Process Quality System ReviewInternal quality system audit against customer requirements
Process Flow ChartDetailed process flow for all operations
Floor Plan LayoutManufacturing floor layout approved
Characteristics MatrixMatrix linking process steps to product characteristics
PFMEAProcess FMEA — all failure modes, AP ratings, H-AP actions complete
Pre-Launch Control PlanControl plan for pre-launch production
Process InstructionsWork instructions for all operations
MSA PlanGauge R&R plan for all measurement systems
Preliminary Process Capability Study PlanPlan for capability studies on special characteristics
Packaging SpecificationsFinal packaging specs including OEM labelling

Gate 3 pass criteria:

  • PFMEA complete, H-AP actions closed or formally accepted
  • Pre-launch Control Plan approved
  • Process instructions complete for all operations
  • Tooling and equipment installed and qualified
  • No unresolved open issues blocking pre-launch build

Phase 4 — Product and Process Validation

Objective: Validate the production process and prepare for PPAP submission.

Key deliverables:

DeliverableDescription
Production Trial RunSignificant Production Run (minimum run to PPAP requirements)
MSA StudiesGauge R&R completed for all special characteristics
Preliminary Process CapabilityCpk study on special characteristics (target ≥ 1.67)
Production Part Approval (PPAP)All 18 PPAP elements complete and submitted
Production Validation TestingFinal validation tests on production parts
Packaging EvaluationProduction packaging validated
Production Control PlanFinal production control plan approved
Quality Planning Sign-OffCustomer approval of PPAP and APQP completion
Management Support Sign-OffInternal management approval for SOP

Gate 4 pass criteria (= PPAP approval):

  • Significant production run completed (minimum 300 consecutive parts per AIAG PPAP 4th ed §4.0, unless the customer specifies otherwise in writing)
  • Dimensional results 100% conforming
  • Cpk ≥ 1.67 on all special characteristics (or customer-approved deviation)
  • %GRR < 30% for all MSA studies
  • PPAP submitted and customer approval received
  • No open concerns from validation testing

Phase 5 — Feedback, Assessment and Corrective Action

Objective: Continuous improvement after SOP — close the loop on any issues found in production.

Key activities:

ActivityDescription
Reduced variationMonitor process capability, reduce common-cause variation
Improved customer satisfactionTrack warranty, field returns, and customer scorecards
Improved delivery and serviceMonitor OTD (on-time delivery) and logistics performance
Lessons learnedDocument lessons learned for future programmes
Control Plan updatesUpdate based on production data and any quality escapes
PFMEA updatesUpdate based on field failures and warranty data

Phase 5 is ongoing. There is no defined end gate — it runs for the life of the programme.


APQP timing — rule of thumb

MilestoneTypical timing before SOP
Programme approval / Phase 1 complete18–24 months
Design release / Phase 2 complete12–15 months
Process design complete / Phase 3 complete8–10 months
PPAP submission4–6 months
PPAP approval (customer)3–4 months
Pre-production builds2–3 months
SOP0

Automotive OEM programmes vary — always confirm with the customer's APQP coordinator.

Validation criteria

At each gate review, verify:

  • All deliverables for the phase are complete (not "in progress")
  • No open H-AP items in DFMEA or PFMEA without approved actions
  • No outstanding design or process concerns without a documented resolution plan
  • Team sign-off obtained from all functions (quality, engineering, manufacturing, purchasing)
  • Customer confirmation received before advancing to next phase

Gate reviews are STOP gates — do not advance until all criteria are met.

Common mistakes

  • Starting Phase 2 before customer requirements are fully understood and documented (Phase 1 incomplete)
  • PFMEA created after process is already running — it must drive process design, not document it
  • Production trial run shorter than 300 consecutive parts without written customer authorisation — the PPAP samples must come from this run; a shorter run requires an explicit customer waiver
  • Capability studies run on off-tool or pre-production parts — must be from production tooling
  • Prototype Control Plan used for PPAP submission — production control plan must be separate
  • MSA studies done after PPAP submission — must be complete before PSW is signed
  • Phase 5 never started — APQP is treated as "done" at SOP rather than as a continuous loop
  • Lessons learned not captured — same problems recur on next programme

Output Format

At the start of each use, ask the user:

"How would you like to receive the output? A — Structured Markdown (formatted tables and sections, ready to copy) B — Plain tables (simplified structure for Excel or Word) C — Narrative report (flowing text for a formal document or email)

Default: A."

Adapt all output sections to the chosen format. If the platform or session context already defines a format preference, skip this question.

Changelog

VersionDateAuthorChange
1.02026-06-06@RBraga01Initial release
1.12026-06-06@migmccAdded 300-part production trial run minimum to Gate 4 criteria and Common Mistakes

Signals

GitHub stars
1k
Forks
316
Last commit
Oct 2026
Advanced
Item type
skill
Key
apqp
Source
github.com/hashgraph-online/awesome-codex-plugins