Critical Chain Scheduler
SkillProductivityCritical Chain Project Management (CCPM) skill with buffer management and resource leveling
Instructions available. Your AI can read the instructions. Execution depends on the setup they require.
Account requirements not reviewed. Check the skill instructions before use; ahel provides instructions and does not run this skill.
Add ahel to your AI once: Claude, ChatGPT, Cursor, Claude Code or Codex. Then ask it to use this.
Then ask your AI: use the Critical Chain Scheduler skill
What this skill tells your AI
The instructions your AI receives, as published by a5c-ai/babysitter in library/specializations/domains/business/operations/skills/critical-chain-scheduler/SKILL.md and read by ahel’s review.
Overview
The Critical Chain Scheduler skill provides comprehensive capabilities for implementing Critical Chain Project Management (CCPM). It supports critical chain identification, buffer sizing and monitoring, resource leveling, and multi-project synchronization.
Capabilities
- Critical chain identification
- Project buffer sizing
- Feeding buffer calculation
- Resource buffer placement
- Multi-project buffer management
- Buffer consumption tracking
- Relay runner behavior monitoring
Used By Processes
- TOC-004: Critical Chain Project Management
- CAP-002: Production Scheduling Optimization
Tools and Libraries
- Project management APIs
- Scheduling optimization tools
- Resource management systems
- Buffer monitoring dashboards
Usage
skill: critical-chain-scheduler
inputs:
project_name: "New Product Launch"
tasks:
- id: "T1"
name: "Design"
duration_50: 10 # 50% confidence estimate
duration_90: 18 # 90% confidence estimate
resources: ["Engineer A"]
predecessors: []
- id: "T2"
name: "Prototype"
duration_50: 5
duration_90: 9
resources: ["Engineer A"]
predecessors: ["T1"]
- id: "T3"
name: "Testing"
duration_50: 8
duration_90: 14
resources: ["Engineer B"]
predecessors: ["T2"]
resource_constraints:
- name: "Engineer A"
capacity: 1
outputs:
- critical_chain
- project_buffer
- feeding_buffers
- resource_buffers
- project_schedule
- buffer_status_report
CCPM vs. Traditional Project Management
| Aspect | Traditional | CCPM |
|---|---|---|
| Task estimates | Include safety | Aggressive (50%) |
| Safety time | Hidden in tasks | Aggregated in buffers |
| Start rule | As soon as possible | As late as safely possible |
| Progress tracking | Task completion | Buffer consumption |
| Resource focus | Utilization | Flow |
Buffer Types and Sizing
Project Buffer
Location: End of critical chain
Size: 50% of critical chain length
Purpose: Protect project due date
Feeding Buffer
Location: Where non-critical path joins critical chain
Size: 50% of feeding chain length
Purpose: Protect critical chain from delays
Resource Buffer
Location: Before resource-constrained critical chain tasks
Purpose: Alert resources to upcoming critical work
Buffer Management
| Buffer Status | % Consumed | Action |
|---|---|---|
| Green | 0-33% | Plan recovery |
| Yellow | 34-66% | Implement recovery |
| Red | 67-100% | Escalate and expedite |
Relay Runner Behavior
- Don't start early
- Work at full effort once started
- Pass work immediately when complete
- Focus on elapsed time, not effort
Integration Points
- Project management systems
- Resource management platforms
- Portfolio management tools
- Time tracking systems
Signals
- GitHub stars
- 2k
- Forks
- 112
- Last commit
- Sep 2026
Advanced
- Item type
- skill
- Key
critical-chain-scheduler- Source
- github.com/a5c-ai/babysitter
More in Productivity
Skill · coreyhaines31
More in Productivitygws-calendar
Skill · googleworkspace
More in Productivitylark-workflow-standup-report
Skill · larksuite
More in Productivitywriting-plans
Skill · obra
More in Productivityenergy-procurement
Skill · affaan-m
More in Productivityhomelab-pihole-dns
Skill · affaan-m
More in Productivity