estimate
SkillProductivityEstimates task effort by analyzing complexity, dependencies, historical velocity, and risk factors. Produces a structured estimate with confidence levels.
Available today. Use it from your connected AI after setup.
No other account needed.
Connect ahel once, and every AI you use reads what you have installed.
Then ask your AI: use the estimate skill
What this skill tells your AI
The instructions your AI receives, as published by negentropy-laby/opendoge in .agents/skills/estimate/SKILL.md and read by ahel’s review.
User Guide
- When to use: Estimates task effort by analyzing complexity, dependencies, historical velocity, and risk factors. Produces a structured estimate with confidence levels.
- Inputs: Command arguments:
/estimate [task-description]; project artifacts referenced below; user decisions and approvals before writes. - Outputs: Primary artifacts, reports, or conversation guidance described below; write files only after user approval.
- Memory-bank writes: None.
- Next steps: Follow the workflow hand-off or next-step guidance below; recommendations do not auto-run and require explicit user command/approval.
Phase 0: Domain Routing
Detect the project domain before estimating:
design/cdd/game-concept.md-> [Game] estimate using game risk factors: mechanic complexity, engine integration, content production, tuning, playtest iteration, platform constraints, and asset dependencies.design/cdd/product-concept.md-> [Product] estimate using product risk factors: API/CLI/UI scope, data model changes, migrations, integration boundaries, security, observability, deployment, and documentation.- If unclear, ask which risk model to use.
Keep game estimation examples; product estimates add a parallel calibration model.
Phase 1: Understand the Task
Read the task description from the argument. If the description is too vague to estimate meaningfully, ask for clarification before proceeding.
Read AGENTS.md for project context: tech stack, coding standards, architectural patterns, and any estimation guidelines.
Read relevant design documents from design/cdd/ if the task relates to a documented feature or system.
Phase 2: Scan Affected Code
Identify files and modules that would need to change:
- Assess complexity (size, dependency count, cyclomatic complexity)
- Identify integration points with other systems
- Check for existing test coverage in the affected areas
- Read past sprint data from
production/sprints/for similar completed tasks and historical velocity
[Product] Product surface scan:
- Identify API endpoints, CLI commands, UI screens, data models, migrations, config files, package/deployment files, docs, and examples that would change.
- Check
docs/architecture/, ADRs,design/cdd/,design/ux/, andproduction/qa/for contract, evidence, and release constraints. - Identify language specialist ownership from
standards/technical-preferences.mdand note whether a Product task needs Python, TypeScript, Rust, Go, devops, security, UX, QA, or lead-programmer review.
Phase 3: Analyze Complexity Factors
Code Complexity:
- Lines of code in affected files
- Number of dependencies and coupling level
- Whether this touches core/engine code vs leaf/feature code
- Whether existing patterns can be followed or new patterns are needed
Scope:
- Number of systems touched
- New code vs modification of existing code
- Amount of new test coverage required
- Data migration or configuration changes needed
Risk:
- New technology or unfamiliar libraries
- Unclear or ambiguous requirements
- Dependencies on unfinished work
- Cross-system integration complexity
- Performance sensitivity
[Product] Product complexity factors:
- API/CLI/UI contract shape and backward compatibility
- Data model or migration impact
- Auth, permission, privacy, or security boundary changes
- Observability, logging, alerting, and operational runbook updates
- Deployment/package/release coupling
- Documentation and SDK/example updates required for public surfaces
- Integration dependencies on third-party APIs, queues, storage, or external services
- Test evidence needed: contract, integration, migration, smoke, load, or user-workflow validation
[Product] Product risk model:
- Low: Internal-only change, no contract/schema/migration, tests already cover the module, docs not affected.
- Medium: One public API/CLI/UI surface changes, docs/examples need updates, one integration or config path is touched.
- High: Breaking contract risk, migration or auth change, deployment impact, multiple modules, data loss/security/privacy exposure, or uncertain stack API.
- Spike required: Unknown third-party API behavior, unverified framework version behavior, unclear migration path, or no existing pattern for the product surface.
Phase 4: Generate the Estimate
## Task Estimate: [Task Name]
Generated: [Date]
### Task Description
[Restate the task clearly in 1-2 sentences]
### Complexity Assessment
| Factor | Assessment | Notes |
|--------|-----------|-------|
| Systems affected | [List] | [Core, gameplay, UI, etc.] |
| Files likely modified | [Count] | [Key files listed below] |
| New code vs modification | [Ratio] | |
| Integration points | [Count] | [Which systems interact] |
| Test coverage needed | [Low / Medium / High] | |
| Existing patterns available | [Yes / Partial / No] | |
**Key files likely affected:**
- `[path/to/file1]` -- [what changes here]
### Effort Estimate
| Scenario | Days | Assumption |
|----------|------|------------|
| Optimistic | [X] | Everything goes right, no surprises |
| Expected | [Y] | Normal pace, minor issues, one round of review |
| Pessimistic | [Z] | Significant unknowns surface, blocked for a day |
**Recommended budget: [Y days]**
### Confidence: [High / Medium / Low]
[Explain which factors drive the confidence level for this specific task.]
### Risk Factors
| Risk | Likelihood | Impact | Mitigation |
|------|-----------|--------|------------|
### Dependencies
| Dependency | Status | Impact if Delayed |
|-----------|--------|-------------------|
### Suggested Breakdown
| # | Sub-task | Estimate | Notes |
|---|----------|----------|-------|
| 1 | [Research / spike] | [X days] | |
| 2 | [Core implementation] | [X days] | |
| 3 | [Testing and validation] | [X days] | |
| | **Total** | **[Y days]** | |
### Notes and Assumptions
- [Key assumption that affects the estimate]
- [Any caveats about scope boundaries]
For product tasks, include this Product-specific extension in the estimate:
### Product Surface Assessment
| Factor | Assessment | Notes |
|--------|------------|-------|
| Public surface changed | [API / CLI / UI / Data / Config / Docs / None] | [contract names] |
| Compatibility impact | [None / additive / breaking-risk / breaking] | [migration or fallback notes] |
| Data or migration impact | [None / small / significant] | [schemas/tables/files] |
| Security/privacy impact | [None / low / medium / high] | [auth/permissions/data exposure] |
| Operational impact | [None / deploy / monitoring / on-call / rollback] | [runbook/evidence needed] |
| Documentation/examples | [None / update / new docs required] | [paths likely affected] |
### Product Test Evidence Needed
| Evidence Type | Needed? | Notes |
|---------------|---------|-------|
| Contract/API or CLI tests | [Yes/No] | |
| Integration tests | [Yes/No] | |
| Migration/config validation | [Yes/No] | |
| Smoke/user-workflow test | [Yes/No] | |
| Performance/load check | [Yes/No] | |
| Docs/example verification | [Yes/No] | |
Output the estimate with a brief summary: recommended budget, confidence level, and the single biggest risk factor.
This skill is read-only — no files are written. Verdict: COMPLETE — estimate generated.
Phase 5: Next Steps
- If confidence is Low: recommend a time-boxed spike (
/prototype) before committing. - If the task is > 10 days: recommend breaking it into smaller stories via
/create-stories. - To schedule the task: run
/sprint-plan updateto add it to the next sprint.
[Product] Product next steps:
- If the task changes a public API/CLI/UI/data contract, recommend
/propagate-design-changebefore implementation. - If the task changes migration, deployment, or package behavior, recommend
/release-checklistor/hotfixdepending on urgency. - If the task has unknown stack behavior, recommend
/prototypeor/setup-engine refresh [stack]before committing to the estimate.
Guidelines
- Always give a range (optimistic / expected / pessimistic), never a single number
- The recommended budget should be the expected estimate, not the optimistic one
- Round to half-day increments — estimating in hours implies false precision for tasks longer than a day
- Do not pad estimates silently — call out risk explicitly so the team can decide