Fix Monte Carlo project completion simulations that give identical dates for all sub-groups (milestones, priorities, epics). Use when: (1) All sub-group predictions converge to the same date despite different remaining counts, (2) Proportional throughput scaling produces flat/identical results, (3) Applying overall scope rate to individual sub-groups causes simulations to hit max_weeks cap and never converge, (4) Building project forecasting tools that predict completion for sub-groups of a larger backlog. Covers hypergeometric draw model for milestones and cumulative priority model for sequential priorities.

Available today. Use it from your connected AI after setup.

Connect ahel once, and every AI you use reads what you have installed.

Then ask your AI: use the Monte Carlo Sub-Group Prediction Scaling skill

What this skill tells your AI

The instructions your AI receives, as published by divinevideo/divine-mobile in .agents/skills/montecarlo-subgroup-prediction/SKILL.md and read by ahel’s review.

Problem

When running Monte Carlo simulations for project completion, predicting dates for sub-groups (milestones, priorities, epics) within a larger project produces identical results for all groups, or simulations diverge and hit the max_weeks cap.

Context / Trigger Conditions

  • Building a project forecasting tool that predicts dates for individual milestones or priority groups within a larger project backlog
  • All sub-group predictions show the same date despite very different remaining counts (e.g., 5-item milestone shows same date as 46-item milestone)
  • Simulations hit max_weeks (104) and produce dates 2+ years in the future
  • Scope rate applied per-group causes negative net velocity (items grow each week)

Root Causes

1. Proportional Scaling is Mathematically Constant

If you scale throughput proportionally:

share = remaining_i / total_remaining
scaled_throughput = overall_throughput * share
weeks = remaining_i / scaled_throughput
      = remaining_i / (overall_throughput * remaining_i / total_remaining)
      = total_remaining / overall_throughput  # CONSTANT for all groups!

Every sub-group predicts the same number of weeks regardless of size.

2. Overall Scope Rate Overwhelms Sub-Group Throughput

If the project's overall scope rate is 50 items/week and you apply it to a sub-group with only 5 remaining items (share = 1.6%), the scaled throughput might be ~0.6/week while scaled scope is ~0.8/week. Net velocity is negative — the simulation never converges and hits max_weeks.

3. GitHub created_at ≠ "Added to Board"

Scope rate calculated from created_at dates reflects when GitHub issues were created, not when they were added to the project board. Bulk triaging or importing old issues inflates the apparent scope rate dramatically.

Solution

Use different simulation models for different sub-group types:

For Sequential Priorities (P0, P1, P2...): Cumulative Model

Higher priorities are completed first. Each priority's prediction includes all higher-priority work that must finish before it:

sorted_priorities = sorted(priorities, key=lambda p: p["name"])
cumulative_before = 0

for p in sorted_priorities:
    effective_remaining = cumulative_before + p["remaining"]
    result = simulate(
        remaining=effective_remaining,
        throughput_history=full_project_throughput,  # NOT scaled
        scope_rate=0.0,  # Don't apply scope per-group
    )
    result.remaining = p["remaining"]  # Show actual remaining
    cumulative_before += p["remaining"]

For Milestones/Epics: Hypergeometric Draw Model

Items from each milestone are randomly drawn from the overall work pool. Smaller milestones finish earlier due to higher variance:

for i in range(n_simulations):
    subset_left = remaining
    pool_left = total_remaining
    weeks = 0
    while subset_left > 0 and weeks < max_weeks:
        throughput = rng.choice(throughput_samples)
        draw_size = min(throughput, pool_left)
        if draw_size > 0 and pool_left > 0:
            other = pool_left - subset_left
            # How many completed items come from this milestone?
            drawn = rng.hypergeometric(subset_left, max(other, 0), draw_size)
            subset_left -= drawn
            pool_left -= draw_size
            pool_left = max(pool_left, subset_left)
        weeks += 1

Key Principles

  1. Don't scale throughput proportionally — it produces identical results
  2. Don't apply overall scope rate to sub-groups — it causes divergence
  3. Use the full project throughput for priority predictions (cumulative model)
  4. Use hypergeometric sampling for milestone predictions (discrete draws)
  5. Show scope rate as informational rather than baking it into per-group MC

Verification

  • Sub-groups with fewer remaining items should predict earlier dates
  • Smaller sub-groups should have wider confidence intervals (more variance)
  • No predictions should hit the max_weeks cap under normal conditions
  • Priority predictions should be ordered (P0 < P1 < P2 < P3)

Example

With throughput of [2, 29, 44, 34, 11, 24, 33, 54, 34, 101, 57, 81, 0] and 303 total remaining items:

Before fix (proportional scaling):

MVP Rel 1 (5 left):   Apr 13    # All identical!
MVP Rel 2 (46 left):  Apr 13
Release 3 (33 left):  Apr 13

After fix (hypergeometric draws):

MVP Rel 1 (5 left):   Apr 6     # Differentiated by size
MVP Rel 2 (46 left):  Apr 13
Release 3 (33 left):  Apr 13
Zap Store (10 left):  Apr 13

Notes

  • The continuous proportional model (subset_throughput = throughput * share) is mathematically equivalent to "everything finishes when the project finishes" because the differential equation d(subset)/dt = -T*(subset/pool) preserves ratios
  • The hypergeometric distribution is the correct statistical model for "drawing without replacement from a mixed pool"
  • For very small sub-groups (< 5 items), the hypergeometric model produces high variance — this is correct and reflects genuine uncertainty
  • Consider capping scope_rate at min(scope_rate, throughput * 0.5) if using it, to prevent divergent simulations

Signals

GitHub stars
265
Forks
55
Last commit
Sep 2026
Advanced
Catalog kind
skill
Gateway key
montecarlo-subgroup-prediction
Source
github.com/divinevideo/divine-mobile